YouTrack Server 2026.2 Help

Migrate a Gantt Chart Report

Gantt charts in YouTrack are also available as a static report. This report generates a Gantt chart based on the underlying data that is stored in each of the issues that match the report filter.

If you would like to transfer your report data to an interactive chart, you can use our built-in migration tool. This tool copies the data from the report and uses that information to create the interactive chart. The original report remains unchanged, which means you can continue using it to report your progress while managing the actual issues on the interactive version.

To migrate data from a Gantt chart report to a new Gantt chart:

  1. From the main navigation menu, select Reports.

  2. Open the report that contains the data that you want to migrate.

    • If this is the first time that anyone has viewed the report without dismissing the banner, click the Go interactive button in the banner.

      Option to migrate to the interactive chart in the report header.
    • If the banner is no longer visible, click the Edit to access the report settings. From here, click the View this report in an interactive Gantt chart link.

      Option to migrate to the interactive chart in the report settings.
  3. Resume working with issues that were displayed on the report in the new interactive chart.

    An interactive Gantt chart in YouTrack.

The original static Gantt chart can still be accessed by clicking Reports in the application header.

The new interactive Gantt chart created can be accessed by clicking Gantt Charts in the application header.

27 March 2026